What a pultrx Line Proposal Includes: Parties, Scope, Acceptance, Documents

Many pages on this site end with the same sentence: the quotation states it. This page shows what that quotation is. A pultrx line proposal has ten sections, in the order below, and each one answers a question a buyer asks before signing for a pultrusion line. Figures (prices, lead time, payment split, warranty term, training days) are written into your proposal, not published here.

On this page

Technical review: Yunkun Gong, Pultrusion Engineer, pultrx

A pultrusion line is bought on paper months before it runs. The proposal is the only place where the line, the parties and the acceptance rules exist together, so its structure matters more than its length. pultrx writes every line proposal in the same ten sections. A machine-only or die-only quotation uses the same sections with the ones that do not apply marked as such, which makes offers for one machine and for a complete line comparable.

Who do you sign with, and who warrants each item?

The first page names the contracting party and the exporter of record (pultrx, Shanghai, with the registered legal name and office address on the document), then lists every partner factory that builds something in the line and the item it is responsible for. Pulling machines, complete lines and resin injection units come from the partner equipment factory named here. Dies and line tooling come from Henan Zhongsheng in Xinxiang. Each builder is the warranty party for its own items, and the proposal states the term and coverage next to the builder's name.

Why the builder is named in the proposal and not on the website

pultrx configures the line and selects the builder for your project. The website therefore describes machine families and ranges. The proposal names the factory, the model and the warranty party for the machine you are buying.

What design inputs is a pultrusion line quotation built from?

The second section repeats the inputs the line was designed around: the profile drawings and revisions, the target output per profile, the resin route (polyester, vinyl ester, epoxy, polyurethane or phenolic), the reinforcement package, the plant voltage and frequency, and the site status. A later change on your side then shows as a change of basis and not as a dispute. If an input was assumed because you had not supplied it, the assumption is written here and flagged for confirmation.

  • Profile drawings with revision numbers and the tolerance class to be held
  • Target output per profile and the planned shift pattern
  • Resin route and the reinforcement package, or a request for the formulation review to propose them
  • Plant electrical supply, compressed air, extraction and floor space available
  • Whether this is a new plant, an added line or a replacement in a running plant

What does the station-by-station line configuration state?

The line is listed in the order the fiber travels: creel, impregnation (open bath or injection box), preforming guides, die station with heating and die table, puller, cut-off saw and run-out table, plus the control cabinet and the data logging that ties them together. Each station carries its configuration values, the builder and whether it is included, separately priced or supplied by you. The pulling machine has its own configuration sheet: puller type, pull force, clamp or track dimensions, speed range, heating zones and controls.

Station list of a pultrx line proposal and what each entry states
StationConfiguration statedBuilder named
Creel and mat standsPackage count, tension control, mat and veil positionsPartner factory (line tooling)
ImpregnationOpen resin bath or closed injection box; metering for polyurethanePartner factory, or the partner equipment factory for the injection unit
Preforming guidesPlate sequence designed with the die; materialsHenan Zhongsheng, with the die
Die stationDie table size, heating zones, control type, die mounting interfacePartner equipment factory
PullerHydraulic, servo-hydraulic or caterpillar; pull force, clamp or track size, speed rangePartner equipment factory
Cut-off and run-outSaw type, cut-length control, run-out length, extraction connectionPartner equipment factory
Controls and dataPLC and HMI, logged signals, export format, remote access if agreedPartner equipment factory
Pultrusion line quotation diagram: builder named per station and payment milestones tied to events from order to SAT
The station list as a pultrx proposal states it, with the builder named for each station, and the payment milestones tied to events (order, drawing approval, signed FAT record, shipment, SAT), lead time counted in working days from drawing approval.

What die and tooling details are listed per profile?

Every launch profile gets its own die line: the drawing it is cut to, the die steel and surface treatment, cavity count, mandrels where the section is hollow, and the preform guides that ship with it. Where the proposal lists a trial pull, it says what is pulled, with which materials and what is recorded. A trial that is not listed is not included. Dies for profiles you add after launch are quoted later as separate tooling.

The drawing package the die section is built from is described in how to specify a pultrusion die

What is included, separately priced, or supplied by the buyer?

The fifth section is a three-column table that resolves the word turnkey. Every item from the station list, the services and the project work appears once, in one of the three columns. The lists below are the standing pattern. Your proposal fills them with the items and prices for your line.

Typically included or separately priced

  • Line design and layout drawing
  • Pulling machine with controls and cut-off, as configured
  • Dies and preform guides for the agreed launch profiles
  • Creels, resin bath or injection system, preformers
  • FAT: trial materials, duration, witnessing and pass/fail criteria
  • Installation support, SAT, operator training and handover records
  • Spare-parts kit with item list and quantities
  • Resin mixing room, QC laboratory and process data logging where requested

Typically supplied by the buyer

  • Building, foundations and utilities to the layout drawing
  • Customs clearance, inland transport and offloading
  • Engineer visas, travel, accommodation and local transport
  • Production raw materials
  • Destination electrical requirements and conformity assessment
  • Product qualification testing
  • Dies for profiles added after launch

How are the FAT protocol and SAT defined before shipment?

The proposal carries the factory acceptance test protocol as an annex, already written. It lists the test items (completeness, pull force, clamp force, speed range and stability, heating zones, control functions and interlocks, voltage and frequency, cut-length repeatability, a trial pull with your die, profile dimensions, documentation), the method for each and the pass criterion to be agreed. It names where the test is run, who may witness it in person or by video, and which payment milestone the signed FAT record releases. The site acceptance test after installation is listed the same way.

The full FAT table with methods and criteria, and the SAT sequence, are in the commissioning and training guide

How are installation, start-up, training, and handover scoped?

Services are written as work packages with a deliverable each: installation supervision, start-up of the first die with a parameter record, operator and maintenance training on your line, and the technical handover. The proposal states who travels, for which packages, and what record you receive at the end of each. Trainee numbers, days on site and follow-up visits are project figures and appear only here.

Which commercial terms are written into the proposal?

Price per configuration in the stated currency. The Incoterm and named place. Payment milestones tied to events (order, drawing approval, signed FAT record, shipment, SAT) and not to dates. Lead time in working days counted from drawing approval, with the trial pull and sample report as separate milestones. Warranty term and coverage per builder. The governing contract language. pultrx publishes none of these figures on the website, which is why a proposal starts from your drawings and not from a price list.

To understand why two proposals for the same profile can differ, read what drives a pultrusion machine price

Which technical documents ship with the pultrusion line?

The ninth section lists the documents that ship with the equipment and the dies, in the contract language: general-arrangement and layout drawings, the utility schedule, operating manuals, electrical and hydraulic schematics, the parts list with the builder's part numbers, die drawings, the signed FAT record and, after start-up, the parameter record for each die. A document that is not on this list is not part of the delivery.

How does the comparison sheet check competing line offers?

The last page restates the proposal on the same scope sheet pultrx asks buyers to use for every offer. A competing quotation with a lower total can then be checked item by item for what it leaves out: dies, upstream stations, FAT, installation, training, spares, freight. The editable version of that sheet is in the resource library.

Download the supplier quotation comparison worksheet

What should you send to request a line proposal?

  1. Profile drawings, or sketches with dimensions and the intended use, for the launch profiles
  2. Target output per profile, or the annual quantity you need to sell
  3. Resin route and reinforcement if already decided; otherwise say so and the formulation review is proposed
  4. Plant voltage and frequency, available floor space and whether the site exists yet
  5. What you want quoted: a complete line, one machine, dies only, or services with equipment you already have

An engineer reviews the request, asks only the missing questions and the Shanghai office issues the proposal in the structure above. No fixed turnaround is promised. The review time depends on how complete the inputs are.

Sources and further reading

Questions buyers ask

Can I get a proposal for one machine or one die instead of a complete line?

Yes. The same ten sections are used. Those that do not apply are marked as not quoted, so a machine-only offer and a complete-line offer from pultrx can be read side by side.

Does the proposal name the factory that builds the machine?

Yes. The parties section names the partner equipment factory, the model and the warranty party for every machine and injection unit, and Henan Zhongsheng for dies and line tooling. The website describes families and ranges. The proposal names the builder for your line.

Will I get a price range before sending drawings?

No. A pultrusion line price follows the profile, the puller and heating configuration, the dies and the scope around the machine, so pultrx does not publish or estimate a range. Send the drawings and output target and the proposal states the price per configuration.

What does the FAT annex commit to?

The test items, methods and the pass criteria to be agreed, the test location, who witnesses and how, and which payment milestone the signed FAT record releases. Equipment acceptance does not establish finished-product conformity to a standard. Product qualification is a separate item.

Who is the contracting party?

pultrx, Shanghai, is the contracting party and exporter of record for the whole line. Its registered legal name and office address are printed on the proposal and the contract. Partner factories build the items and warrant them, as named per item.

Summary

What does a pultrusion line proposal from pultrx include?

One document, ten sections: the parties and who warrants what; the basis of design taken from your drawings and output; a station-by-station line configuration with the builder named per item; dies and tooling per launch profile; a scope matrix of included, separately priced and buyer-supplied items; the factory acceptance test protocol; installation, start-up and training scope; commercial terms; the documents delivered with the line; and a comparison sheet so you can set it against other offers.

Issued by
pultrx, Shanghai: the contracting party for the whole line
Builders
Named per item: the partner equipment factory for machines and injection units, Henan Zhongsheng for dies and line tooling
Warranty
Each builder warrants its own items; term and coverage written in the proposal
Acceptance
FAT protocol with written pass/fail criteria before shipment; SAT after installation
Figures
Price per configuration, lead time in working days from drawing approval, payment milestones tied to events: all in the proposal, none published
To request one
Profile drawings, target output, resin route, plant voltage and frequency, site status

Published by pultrx, an integrated pultrusion technology provider working with Henan Zhongsheng as a partner factory. This is a buyer planning guide; the manufacturer confirms project specifications in writing.

Ready to move from reading to a scoped quotation?

Request a line proposal

Send a cross-section drawing. Get a scoped quotation.

Every quotation names the manufacturer, the exporter of record and the warranty party, and lists what is included.